Changelog smartProject – Release 67
Released: 2023-09-13
App Version: 22.5.10679.5
ID 13748
ID | Type | Area | Title | External reference |
---|---|---|---|---|
13748 | Problem | smartProject | Lack of resource capacity for monthly working time models | 6776 |
Details

- If a monthly working time model is assigned to a resource, no capacity is created with the "Automatic capacity allocation" function. This is incorrect, as it is not possible to plan the deployment of these resources in this way
- This has been corrected.
- Automatic capacity distribution works correctly if a monthly working time is set in the working time model.
- This has been corrected.
ID 14529
ID | Type | Area | Title | External reference |
---|---|---|---|---|
14529 | Problem | smartProject | Application to superiors can be freely selected |
Details

- If a request is created, the line manager is removed from the employee card. However, it is still possible to enter anyone else as a superior. Among other things, it is possible to authorise the request yourself.
- This has now been corrected
- If the supervisor is stored in the employee card, the request to the supervisor can no longer be can no longer be changed in the request. This also applies if you change the employee and the manager is filled in for this employee.
- If the supervisor on the employee card is not filled, the supervisor can be can be changed as often as required in the application
- This has now been corrected
ID 14979
ID | Type | Area | Title | External reference |
---|---|---|---|---|
14979 | Problem | smartProject | Amount for provisional retention is missing for debtor items |
Details

- The "Amount provision. Retention" from the project card in the "Provisional retention" tab is not taken into account when posting to the debtor items.
- This has been corrected and the "Amount provision. Retention" is taken into account when posting the invoice in the customer items.
ID 15783
ID | Type | Area | Title | External reference |
---|---|---|---|---|
15783 | Problem | smartProject | Error in invoicing in the project for deleted project budget lines |
Details

- If there are budget items in the project items that have already been deleted, these are not taken into
not taken into account in accounting.
- This has been corrected.
ID 16699
ID | Type | Area | Title | External reference |
---|---|---|---|---|
16699 | Feature | smartProject | ARZE - Employment of external companies - Optimisation of invoice verification for external employees | 8276 8270 |
Details

- Currently, the time recording of employees from external companies and the corresponding invoice from the personnel
of the personnel service provider have to be reconciled manually.
- The implementation takes place with provisions for purchases of external services
- In the first step, the "Resource card ", the resource that is to be activated for the booking of external external services, the selection External must be made in the "General " tab in the "Type " field
- In the next step, the vendor number of the personnel service provider to which the resource is to be assigned must be entered in the "Vendor no. " field in the "Resource card " on the "Vendor " tab.
- In addition, the accounts "Service receipt account (interim) " and "Service account (interim) " must be entered in the "Setup posting matrix ".
- The "Project purchasing - purchase orders " function from the "Create consumption of external resources " creates purchase orders for all consumption of external services recorded via time recording or the project book sheet.
- The implementation takes place with provisions for purchases of external services
ID 17250
ID | Type | Area | Title | External reference |
---|---|---|---|---|
17250 | Feature | smartProject | Add favourites when changing day |
Details

- When changing the day, the stored favourites should be automatically transferred to the new day.
automatically.
- An adjustment for calling up favourites has been implemented in time recording. + In the view of the daily time recording, the favourites are automatically retrieved and inserted into the sheet when the page is turned to the next day.
ID 17501
ID | Type | Area | Title | External reference |
---|---|---|---|---|
17501 | Feature | smartProject | Rearrange menu items 2 |
Details

- Neue Anordnung der Menüpunkte "Matrix Feldberechnung", "Mögliche Lieferanten zuweisen" und
"Einrückung nach Rechts" in Ansicht "Projektbudget" – Ansicht "Einkaufsmengenüberwachung"
- In der Ansicht "Projektbudget" – Ansicht "Einkaufsmengenüberwachung" wurden die Punkte
- "Matrix Feldberechnung" unter "Aktionen" → "Budget",
- "Mögliche Lieferanten zuweisen" unter "Aktionen" → "Budget",
- "Einrückung nach Rechts" – "Aktionen" → "Zeilen"
verschoben
- In der Ansicht "Projektbudget" – Ansicht "Einkaufsmengenüberwachung" wurden die Punkte
ID 17790
ID | Type | Area | Title | External reference |
---|---|---|---|---|
17790 | Feature | smartProject | Conversion of old legacy views (project overview, etc.) |
Details

- Old views (legacy views) must be converted to the new modern views in smartProject, as the legacy views are no longer available with BC23.
- All overview pages have been adapted
ID 18264
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18264 | Feature | smartProject | Double query "Book invoice" |
Details

- When posting unbooked sales deliveries, the query "Would you like to book the invoice?
book the invoice" twice if the query is confirmed with "No".
- This has been adjusted.
ID 18332
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18332 | Feature | smartProject | DACH translations | 8708 |
Details

- In the databases, different languages (either German or English) are often displayed for different
German or English) are often displayed in the same areas for different employees.
- This has been corrected.
- The translation errors of menu items have been fixed in the DACH area.
- This has been corrected.
ID 18353
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18353 | Feature | smartProject | In the cost monitoring view, the percentage of completion is always 0%. | 8851 |
Details

- Although the percentage of completion has been registered, it is set to 0% in the cost monitoring view
- This has been corrected.
- If the percentage of completion has been registered, this value is transferred to the cost monitoring.
- This has been corrected.
ID 18457
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18457 | Feature | smartProject | It is no longer possible to change the line type after posting | 8615 |
Details

- If project bookings have been made, it must no longer be possible to change the line type to Heading in the project budget / HOAI view, as otherwise the linked items can no longer be called up.
- This has been corrected.
- After project bookings have been made, it is no longer possible to change the line type in Heading in the project budget / HOAI view.
- This has been corrected.
ID 18632
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18632 | Feature | smartProject | Fix smartProject error Nextmajor (BC23) |
Details

- For BC23, current error messages in smartProject app must be fixed.
- This has been corrected.
ID 18469
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18469 | Feature | smartProject | Learning tours in smartPROJECT |
Details

- For smartProject, small learning tours are to be implemented on the smartProject pages analogue to the standard are to be implemented.
- This was implemented in the first step on the project card.
- There is a learning tour on the project map analogue to the BC standard.
- This was implemented in the first step on the project card.
ID 18470
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18470 | Problem | smartProject | IBL records are no longer drawn since February 2023 | 8844 |
Details

- Resource acquisition prices in connection with project reference are not drawn correctly.
- This has been corrected.
- The prices with project reference stored in the resources settings. Price items with project reference are drawn correctly.
- This has been corrected.
ID 18478
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18478 | Problem | smartProject | Sample invoice including payment amount | 7511 |
Details

- Adjustment of the invoice document according to the sample template.
- The invoice document has been adjusted.
- For project invoices that already contain advance payment invoices, there is an addition for the clearing documents. The current payment amount for the settlement payment is saved in the invoice line. The field is currently not displayed. The field can be found via the page check under the name "PMS Payment Applied Doc".
- The cumulative total of payments for the respective invoice is displayed in the field.
- The field contains the payment amount at the time the invoice is posted.
- The invoice document has been adjusted.
Note:
The field is not updated dynamically as soon as further payments are posted.
ID 18536
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18536 | Problem | smartProject | Consumption with individual sales price cannot be invoiced | 8923 |
Details

- If you post consumption with an individual sales price to a project budget line, the error message "The field number of the table sales line contains a value (L011) that was not found in the corresponding table (resource). " appears when creating the invoice.
- This has been corrected.
ID 18657
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18657 | Problem | smartProject | Consumption with individual sales price cannot be invoiced | 8923 |
Details

- The clearing of down payment invoices in the payment run is not possible because the selection of the invoice/credit note type is not possible.
- This has been corrected. + A function for transferring recorded times of external employees to purchase orders has been developed. It is now possible to post accruals from purchases.
ID 18749
ID | Type | Area | Title | External reference |
---|---|---|---|---|
18749 | Problem | smartProject | Incorrect numbering according to internal block | 9020 |
Details

- when creating the project budget, the first 4 items were created and then set as an internal block. A further item should be added. The additional position does not have the correct consecutive numbering.